For all right-of-way construction (existing or proposed right-of-way), inspections will be done by the City Engineer, or the designated inspectors for the City Engineer. The applicant shall notify the City at least two business days in advance of each of the following required inspections:

Inspection No. 1: Clearing and grubbing, embankment and excavation, and temporary water detention/retention and siltation control.

Inspection No. 2: Complete drainage system prior to cover; including pipe connections, connections to structures, compaction, etc.

Inspection No. 3: General street; when the drainage system, underground utilities, and street grading to suitable subgrade are complete.

Inspection No. 4: General street; when the crushed gravel surfacing has been placed.

Inspection No. 5: General street; curb, gutter and sidewalk and other appurtenances if required by the approved plans.

Inspection No. 6: General street; while the paving is in progress.

Inspection No. 7: Overall street; after paving, cleaning of drainage system and all necessary cleanup, striping, buttoning, monumentation, and all street delineation work.

Lack of inspection(s) does not relieve the applicant from ensuring proper construction and/or compliance with the approved plans and specifications. [Ord. 501 § 3, 2009.]