At the time of application for a right-of-way permit, the applicant shall notify all other public and private utility entities known to be using or proposing to use the same right-of-way of the proposed timing of such construction. Within seven days of receiving this notification, any such entity notified may request a delay of the proposed construction to coordinate other right-of-way construction with the applicant.

The City Engineer may approve a delay of up to 90 days, except in case of emergencies, if he/she determines that such delay will reduce the inconvenience to City street users from construction activities and that the delay will not create undue economic hardship on the applicant. The City Engineer shall also coordinate the approval with City street improvements and maintenance and may also delay the construction under the same circumstances. [Ord. 501 § 3, 2009.]